Projected Schedule

  Week 1
     o   The project was introduced and reviewed
     o   Blogger account was setup to report progress
     o   Pre-existing design solution was discussed
  Week 2
     o   Building materials were introduced
     o   Supplies were organized and selected
     o   For next week: test supplies, work on LED matrix design and publish a design proposal
   Week 3
     o   Finalize LED matrix design
     o   Begin assembly of matrix
     o   For next week: order necessary parts for final circuit
   Week 4
     o   Complete assembly of LED matrix
     o   Attach matrix to power circuit
     o   For next week: investigate measuring light and heat intensity
   Week 5
     o   Measure light and heat output of the LED matrix
     o   Begin modifying circuit for variable intensity
     o   For next week: complete variable intensity modifications
   Week 6
     o   Measure light and heat intensity at multiple power settings
     o   Begin designing wearable assembly
     o   For next week: investigate LED heat dissipation
   Week 7
     o   Finalize wearable design incorporating potential heat dissipation
     o   Begin assembly of final wearable design
     o   For next week: order necessary parts for final wearable design
   Week 8
     o   Complete wearable design
     o   Measure light and heat intensity of wearable design
     o   For next week: begin working on final report and presentation
   Week 9
     o   Investigate possible improvements and next steps for the design
     o   Work on final report and presentation
     o   For next week: complete final report and presentation
   Week 10:
     o   Present design
     o   Turn-in report